Assessment: DC Arc Fault in MC4 Connector Causes Cable Fire — EUR 127,000 Damage to 180 kWp Rooftop System

Assessment type: Fire cause investigation / Forensics System size: 180 kWp polycrystalline Region: Rhine-Main area Period: March – May 2025
Assessment summary:
Thermal Escalation Chain — DC Arc Fault Contact fault Contact resistance R > 0.5 Ω ΔT: +15 K Arc fault Serial DC arc T > 300 °C P = 180 W local Insulation failure Riso < 40 kΩ T > 450 °C Polymer pyrolysis Cable fire Open flame T > 650 °C DC cable fire load Module fire Roof structure T > 900 °C Building damage Weeks–months Seconds Minutes < 60 sec. immediate Without AFCI detection: Total duration from contact fault to fire under 10 minutes possible Damage amount in this case: EUR 287,000 (building + system + business interruption)

What was the starting point of the investigation?

On March 12, 2025, the Frankfurt-East fire department was called to a fire on the flat roof of a commercial building (logistics company). The fire could be traced to a section of the PV system. The building insurer immediately commissioned a forensic expert assessment for fire cause investigation.

Situation found during initial inspection (March 14, 2025)

During the initial inspection three days after the fire event, the following was observed:

ObservationLocationAssessment
Melted DC cable insulation over 1.2 m lengthString 7, transition Row 3→4Fire origin
Thermally deformed MC4 connector (copper core visible)String 7, positive leadPrimary fire cause
Melt beads on copper strands (bead formation)Connector jointArc fault evidence
Damaged roof waterproofing membrane (3.4 m²)Below fire locationConsequential damage
5 modules with backsheet burnsString 7+8, Rows 3–4Consequential damage

How was the DC arc fault verified?

The forensic analysis comprised:

Metallurgical examination of melt beads

The copper melt beads found at the damage point (diameter 1.2–2.8 mm) showed the microstructure typical of serial DC arc faults under scanning electron microscopy (SEM): uniform solidification front, fine dendritic structure, and absence of oxide layers in the interior. The melting temperature of copper (1,085 degrees C) was locally exceeded — consistent with arc temperatures of 3,000–6,000 degrees C at the core.

Resistance measurement on the damaged connector

The remaining MC4 connector on the opposing lead (negative pole, not destroyed by fire) showed a contact resistance of 2.8 ohm upon measurement. The normal value for a correctly crimped MC4 connector is <0.5 milliohm — the deviation is thus a factor of 5,600.

Forensic finding: The crimp sleeve had not been fully pressed onto the stripped conductor. An air gap of approximately 2 mm remained, in which over 5 years of operation through micro-vibrations (wind) and thermal cycling, increasing contact resistance developed. At full load (Isc approx. 9.8 A, Voc approx. 720 V DC), a serial arc fault formed that ignited the cable insulation.

What timeline led to the fire?

June 2019

Installation of the 180 kWp PV system by a subcontractor of the general contractor

2019–2023

Normal operation, no regular maintenance or thermography inspections performed

Summer 2024

Monitoring registers slight yield decline in String 7 (-3.2%) — not investigated

March 12, 2025, 1:42 PM

Fire alarm on the upper floor triggers, fire department arrives at 1:51 PM, extinguishes smoldering fire on roof surface

March 14, 2025

Initial inspection by expert assessor, securing of evidence

April 2025

Laboratory analysis of melt beads, SEM examination, preparation of assessment

May 2025

Assessment submitted to insurer, settlement initiated

What was the total economic damage?

Damage calculation (expert determination):
ItemAmount
Replacement of 23 modules + DC cabling String 7+8EUR 34,500
Roof waterproofing membrane repair (3.4 m² + connection work)EUR 12,800
Scaffolding + crane for roof accessEUR 8,200
Lost yield (6 weeks total system shutdown)EUR 14,300
Inspection of all 168 connectors (thermography + resistance)EUR 6,400
Electrical specialist + recommissioningEUR 4,800
Assessment costs (forensics + laboratory)EUR 22,000
Business interruption logistics operation (partial area)EUR 24,000
Total damageEUR 127,000

What recommendations were issued?

The assessment recommended:

  1. Complete inspection of all remaining MC4 connectors using thermography under load and resistance measurement
  2. Installation of an AFDD (Arc Fault Detection Device) per DIN EN 63027 in the generator junction box
  3. Introduction of an annual maintenance routine with thermography inspection per DIN EN 62446-2
  4. Liability claim against the installing subcontractor (installation error — faulty crimp)
Expert assessment: The fire was in all probability preventable. A single thermography inspection (cost: approx. EUR 800–1,200) would have detected the elevated contact resistance as early as 2023. The lack of maintenance of DC connector joints is a widespread but underestimated risk in the industry. Statistically, faulty MC4 connections account for approximately 35% of all PV fires in Germany.

Similar case? We can help.

Independent assessment by TUV-certified expert assessors — operating across Europe.

Request a consultation

Related articles

Last updated: 2026-06-16 | Author: Christoph S. Prestele, TUV-certified expert assessor | PV-BESS-Assessor.com