A municipal utility in North Rhine-Westphalia planned the acquisition of a used 8 MWh container-scale storage system (NMC technology, 4 MW rated power, first commissioned in 2022) for deployment in the frequency regulation market (FCR/aFRR). The seller (project developer) declared an SOH of 87% based on BMS-internal data. Given the transaction volume (purchase price: EUR 2.1 million), the buyer commissioned an independent SOH assessment.
| Day | Test | Method |
|---|---|---|
| 1 | Reference capacity test | Full discharge 0.33C at 25 °C (climate-controlled), 3 cycles |
| 2 | Impedance spectroscopy (EIS) | 10 mHz–10 kHz, sample of 48 cells from 4 containers |
| 3 | Power test | Pulse load 1C / 30 s, voltage drop analysis |
| 4 | BMS log forensics | Operating history: cycles, temperatures, deep discharge events |
| Container | Nominal capacity | Measured capacity | SOH |
|---|---|---|---|
| Container 1 | 2,000 kWh | 1,612 kWh | 80.6% |
| Container 2 | 2,000 kWh | 1,574 kWh | 78.7% |
| Container 3 | 2,000 kWh | 1,598 kWh | 79.9% |
| Container 4 | 2,000 kWh | 1,562 kWh | 78.1% |
| Total | 8,000 kWh | 6,346 kWh | 79.3% |
The EIS measurement on 48 representative cells showed:
| Parameter | New value (datasheet) | Measured (average) | Increase |
|---|---|---|---|
| Ohmic resistance R0 | 0.8 m ohm | 1.14 m ohm | +42% |
| Charge transfer resistance Rct | 1.2 m ohm | 2.1 m ohm | +75% |
| Warburg impedance (diffusion) | 0.4 m ohm s^0.5 | 0.7 m ohm s^0.5 | +75% |
The increased impedance correlates with the capacity degradation and indicates SEI layer growth and loss of active lithium — typical aging mechanisms in NMC after intensive cycling operation.
Based on the semi-empirical degradation model (Arrhenius + cycle aging), continuing the previous operating profile (1.2 full cycles/day, FCR) yields:
| Scenario | Remaining life to EOL (70% SOH) |
|---|---|
| Seller's claim (SOH 87%) | 6.8 years |
| Expert prognosis (SOH 79.3%) | 4.2 years |
| Conservative (worst case) | 3.4 years |
| Factor | Value reduction |
|---|---|
| Capacity deficit 616 kWh x market value | EUR 154,000 |
| Shortened remaining life (2.6 years less x annual revenue) | EUR 156,000 |
| Increased degradation rate (risk premium) | EUR 30,000 |
| Recommended purchase price reduction | EUR 340,000 |
Recommendation: Reduce purchase price from EUR 2.1 million to a maximum of EUR 1.76 million — or withdraw from the purchase.
Similar case? We can help.
Independent evaluation by TUV-certified expert assessors — operating Europe-wide.
Request a consultationLast updated: 2026-06-16 | Author: Christoph S. Prestele, TUV-certified expert assessor | PV-BESS-Assessor.com