PV & BESS Assessor Bonn — Technical Connection Requirements Bonn-Netz

TL;DR — TAB Bonn-Netz Bonn:

As assessors, we prepare reports in Bonn and the Rhein-Sieg district for system operators, investors, and courts. The historic building stock in Bad Godesberg and Bonn's Suedstadt requires particular care with PV projects — this is precisely where knowledge of Bonn-Netz's TAB proves crucial for a standards-compliant installation. In disputes over grid connection requirements, we mediate as a neutral authority.

Note: The grid operator's TAB supplement the nationally applicable VDE application rules. The current version on the Bonn-Netz website is always authoritative.

What are the special features of the Bonn grid area?

Bonn-Netz supplies the federal city of Bonn with approximately 330,000 inhabitants. In the former government quarter and the Gruenderzeit districts, many existing buildings are equipped with older meter cabinets that need to be modernized when installing PV.

Solares Bonn and heritage law: what applies in Bonn

The city funds solar systems through the “Solares Bonn” programme. Under the guideline in force since August 2025, residential buildings with up to three units receive EUR 100 per kWp if the suitable roof area is fully covered. For apartment buildings with four or more units, facade systems and listed buildings, up to EUR 300 per kWp is possible. In October 2025 the funds were exhausted. According to Haus & Grund Bonn/Rhein-Sieg, EUR 800,000 has been available again since 1 January 2026. The application must be filed before the installer is commissioned.

For listed buildings, decision guidelines issued by the North Rhine-Westphalia building ministry have applied since 8 November 2022. Solar systems not visible from public space are generally to be permitted. Visible systems can be approved if they are reversible, preserve the historic fabric and blend in visually, for example matt modules without frames or with frames of the same colour. The City of Bonn has published its own guidelines for listed buildings and heritage areas.

For listed properties in Bonn, our assessment compares the installed system with the heritage permit and the funding conditions. If the execution deviates, both the permit and the grant may be called into question.

Which standards apply to PV systems in the Bonn grid area?

StandardScopeRelevance for PV
VDE-AR-N 4100TAR low voltageMandatory: meter location, service entrance, protection concept
VDE-AR-N 4105Generation systems on LV gridMandatory for connection to the low-voltage grid
VDE-AR-N 4110TAR medium voltageMandatory for connection to the medium-voltage grid
Supplementary TAB Bonn-NetzRegional supplementsGrid operator-specific requirements

How does the PV system registration process work at Bonn-Netz?

  1. Electrical contractor: Only registered installers submit the registration (exception: balcony power plants).
  2. Grid compatibility assessment: For systems from approx. 30 kWp, Bonn-Netz checks the grid's absorption capacity.
  3. Commissioning application: Data sheet, site plan, circuit diagram, conformity certificates.
  4. Meter location and initial verification: Meter location per VDE-AR-N 4100 and TAB, initial verification per DIN VDE 0100-600.
  5. Commissioning: Bonn-Netz installs the bidirectional meter, followed by the mandatory MaStR registration.

What are the requirements for the meter location?

RequirementSpecification
Meter typeeHZ, three-point mounting
Surge protectionType 1+2 combined arrester (mandatory for new systems)
SLS switchselective circuit breaker upstream of the meter
Space reserve1 slot for smart meter gateway
Equipotential bondingto main earthing busbar
Practical tip: Meter cabinets from before about 2010 often fall short. Modernisation: EUR 1,000 to 2,500.

Protection Concept PV/BESS System — Single-Line Diagram

PublicGrid (Bonn-Netz) ServiceEntrance/Meter Anti-IslandingVDE-AR-N 4105Decoupling Prot. CouplingSwitch Inverter PV ArrayDC/AC BESSBattery + BMS Single-Line Protection Concept PV/BESS — Bonn | Grid Operator: Bonn-Netz Standards: VDE-AR-N 4100 (Meter) · VDE-AR-N 4105 (LV Feed-in) · VDE-AR-N 4110 (MV connection)

How are balcony power plants registered with Bonn-Netz?

Plug-in generation systems up to 800 W can be registered with Bonn-Netz through a simplified process.

Grid Connection Process Overview

Application toBonn-Netz GridCompatibility Meter Location& Connection CommissioningProtocol Feed-inApproval FormsSite PlanData Sheets Short-CircuitCalculationGrid Capacity eHZ / TABWiringCT Measurement VDE TestingInsulation TestProtection Test Market MasterData Register§19 EEG Expert assessment recommended for: Grid compatibility · Protection concept · Commissioning · Defect inspection Grid Connection Process Bonn-Netz — Bonn | Source: PV-BESS-Assessor.com
Since 16 May 2024 (Solar Package I): plug-in solar devices up to 800 VA inverter and 2,000 Wp module capacity. Registration in the Market Master Data Register is mandatory; registration with the grid operator is only needed if a feed-in tariff is claimed (VDE FNN).

Important Documents and Forms

TAB & Requirements (Bonn-Netz) Market Master Data Register VDE-AR-N 4100 Clearingstelle EEG|KWKG

Which transmission system operator is responsible in Bonn?

Bonn is located in the Amprion control area. The responsible transmission system operator (TSO) is Amprion GmbH. Amprion is responsible for system stability in the extra-high voltage grid (220/380 kV).

Grid compatibility: Assessments mostly concern the distribution level (Bonn-Netz). Above 1 MWp, coordination with Amprion may be required.
LevelOperatorVoltage LevelRelevance for PV/BESS
Transmission gridAmprion220-380 kVSystem stability, EEG feed-in
Distribution gridBonn-Netz0.4-20 kVTAB, grid connection, meter location
Customer systemSystem operator0.4 kV (LV)PV array, BESS, inverter

What are typical challenges for PV and BESS in Bonn?

Regional factors for planning and assessment in Bonn:

Federal Quarter and Government Buildings

Bonn's Federal Quarter with former government buildings is increasingly being developed with solar. The buildings of the Federal Republic are subject to special security requirements — PV assessments must meet extended requirements here.

Hillside Locations at the Siebengebirge

Bonn's eastern districts (Bad Godesberg, Mehlem) are situated at the Siebengebirge hills. Slope angle and shading from forest stands require precise yield calculations with terrain models.

Flood Protection Rhine Floodplains

Bonn is partially located in the Rhine flood zone. BESS in Beuel and the Rheinaue require installation above the HQ200 level and watertight enclosures for power electronics.

Deutsche Telekom and Post: Campus PV

The Bonn corporate headquarters (Telekom, Post/DHL) are driving large rooftop PV projects. Systems above 1 MWp require dedicated protection concepts and coordination with Bonn-Netz.

When is an expert assessment advisable?

OccasionOur Service
Acceptance assessmentTAB conformity check, defect report
Dispute with grid operatorIndependent technical evaluation
Systems from 30 kWp, medium voltage, capacity bottleneckGrid compatibility assessment, grid analysis, alternative concepts
Defect assessmentDIN VDE 0100-600, thermography, EL

Frequently Asked Questions — TAB Bonn-Netz Bonn

Which TAB apply to PV systems at Bonn-Netz Bonn?▼

VDE-AR-N 4100 and 4105 (low voltage) or 4110 (medium voltage) plus supplementary TAB of Bonn-Netz GmbH.

How do I register a PV system with Bonn-Netz?▼

Exclusively through a certified electrical contractor. Details: Bonn-Netz website.

Do I need a new meter cabinet in Bonn?▼

Must comply with VDE-AR-N 4100 and supplementary TAB. Older cabinets (pre-2010): eHZ, surge protection, SLS. Cost: EUR 1,000-2,500.

How much does a PV or BESS assessment cost in Bonn?▼

Depends on system size and scope. Contact: info@pv-bess-assessor.com or +49 89 97 31 37 43.

When do I need an expert assessment?▼

For systems from 30 kWp, medium voltage, grid compatibility issues, disputes with the grid operator, acceptance of commercial systems.

Independent PV or BESS assessment in Bonn?

We know the TAB of Bonn-Netz from daily practice. Get in touch.

Contact Us

Contact Details Bonn-Netz GmbH

AddressBonn-Netz GmbH, Sandkaule 2, 53111 Bonn
Phone0228 711-0
Emailnetzanschluss@bonn-netz.de
WebsiteBonn-Netz — TAB

Related Topics

On-site assessments — where we work

We assess nationwide. These pages summarise the TAB of each grid operator:

Augsburg Berlin Bielefeld Bremen Dortmund Dresden Düsseldorf Duisburg Frankfurt Hamburg Hannover Karlsruhe Köln Leipzig Mannheim München Münster Nürnberg Stuttgart

Last updated: 2026-11-03 | Source: Bonn-Netz GmbH