Typical questions at acceptance and under warranty
Is the large-scale storage system ready for acceptance?
The acceptance test of a 20 MWh system under IEC 62619 and VDE-AR-E 2510-50 found seven deviations, three of them safety-relevant. Ventilation in two containers reached 48 % of the target air flow.
Acceptance test to IEC 62619 → · What IEC 62619 covers →
Does a district storage system meet VDE-AR-E 2510-50 before commissioning?
A 2 MWh system in a residential area showed twelve deviations, four of them safety-critical. Commissioning remained prohibited until they were fixed.
Conformity test of a district storage system → · Requirements of VDE-AR-E 2510-50 →
Which evidence does the building authority require for a large storage system?
For a 40 MWh system in a Bavarian commercial zone, the authority required a UL 9540A assessment. The project was approvable with 6 m between containers and deflagration venting.
UL 9540A evaluation for the building permit → · The test levels of UL 9540A →
Is the yield shortfall caused by the string layout?
In a 6.8 MWp solar park, modules of different power classes were installed in the same string, and 23 strings had corroded connectors.
IV curve analysis of a solar park → · How IV curve measurement works →
Frequently asked questions — EPC & contractors
The client refuses acceptance — what can you do?
We inspect the plant neutrally against the contractually agreed standards and document the actual condition. The report shows whether there are grounds to refuse acceptance and separates genuine defects from unjustified demands.
A module or inverter manufacturer rejects the claim — can you help?
Yes. Using electroluminescence, IV curve measurement and laboratory analysis we prove serial faults and component defects and assign responsibility, as a basis for your recourse claim.
Can you attend a site inspection in evidence proceedings at short notice?
We respond to enquiries within 24 hours and align with the court calendar where deadlines apply. Offices in Munich and Frankfurt, operating across Europe.
We want to sell a developed project — can you support this?
Yes. With a vendor due diligence we prepare your technical documentation on the seller side, for ready-to-build projects as well as existing plants. A cleanly documented technical baseline shortens the buyer review and supports the price.
What does an independent acceptance cost?
After a short description of plant size and scope of inspection you receive a transparent fixed-price offer from us, usually within 24 hours.
Request a quote
Tell us about your project or dispute. We will respond within 24 hours with an initial assessment and a fixed-price offer.