PV & BESS Assessor Augsburg โ€” Technical Connection Requirements swa Netze

TL;DR โ€” TAB swa Netze Augsburg:

In our assessment projects for photovoltaic and battery storage systems in the greater Augsburg area, we regularly encounter questions regarding the technical connection requirements of swa Netze. Whether acceptance of a commercial PV system in the Augsburg-Sued industrial areas, defect assessment of an existing system in Lechhausen, or technical supervision of a medium-voltage connection in the Innovationspark โ€” TAB conformity is always a central checkpoint in our assessments.

Note: The grid operator's TAB supplement the nationally applicable VDE application rules. The current version on the swa Netze website is always authoritative.

What are the special features of the Augsburg grid area?

swa Netze GmbH operates the power distribution grid in the Augsburg area serving approximately 300,000 inhabitants. The combination of old town locations with listed buildings and modern industrial areas in the south of the city leads to very different grid capacities. The municipal FKG subsidy program from Munich does not apply here โ€” Augsburg has its own municipal climate protection programs.

Which standards apply to PV systems in the Augsburg grid area?

StandardScopeRelevance for PV
VDE-AR-N 4100Technical connection rules low voltageMandatory โ€” meter location, service entrance, protection concept
VDE-AR-N 4105Generation systems on LV gridMandatory for PV โ‰ค 135 kW
VDE-AR-N 4110Technical connection rules medium voltageMandatory for PV > 135 kW
Supplementary TAB swa NetzeRegional supplementsGrid operator-specific requirements
DIN VDE 0100-600Initial verification of electrical installationsMandatory inspection before commissioning

How does the PV system registration process work at swa Netze?

  1. Engage a certified electrical contractor: Only registered installers may submit the registration (exception: balcony power plants).
  2. Grid compatibility assessment: For systems from approx. 30 kWp, swa Netze checks the grid's absorption capacity.
  3. Commissioning application: The installer submits data sheets, site plan, circuit diagram, and conformity certificates.
  4. Prepare meter location: Must comply with VDE-AR-N 4100 and the supplementary TAB.
  5. Installation and initial verification: Testing per DIN VDE 0100-600 by the electrical contractor.
  6. Meter installation and commissioning: swa Netze installs the bidirectional meter. MaStR registration is mandatory.

What are the requirements for the meter location?

RequirementSpecification
Meter typeeHZ in three-point mounting system
Surge protectionType 1+2 combined arrester (mandatory for new systems)
SLS switchSelective line protection switch upstream of the meter
Space reserveMin. 1 slot for smart meter gateway
Equipotential bondingConnection to main earthing busbar
Practical tip: Older meter cabinets (pre-2010 approx.) often do not meet current requirements. Modernization costs: EUR 1,000-2,500. Have them checked in advance!

Protection Concept PV/BESS System โ€” Single-Line Diagram

PublicGrid (swa Netze) ServiceEntrance/Meter Anti-IslandingVDE-AR-N 4105Decoupling Prot. CouplingSwitch Inverter PV ArrayDC/AC BESSBattery + BMS Single-Line Protection Concept PV/BESS โ€” Augsburg | Grid Operator: swa Netze Standards: VDE-AR-N 4100 (Meter) ยท VDE-AR-N 4105 (LV Feed-in) ยท VDE-AR-N 4110 (MV from 135 kWp)

How are balcony power plants registered with swa Netze?

Since 2024, balcony power plants up to 800 W inverter power can be registered through a simplified process at swa Netze. Registration is done via the digital feed-in portal. Contact for installers: Tel. 0821 6500-8977 (Mon-Fri 08:30-10:00).

Grid Connection Process Overview

Application toswa Netze GridCompatibility Meter Location& Connection CommissioningProtocol Feed-inApproval FormsSite PlanData Sheets Short-CircuitCalculationGrid Capacity eHZ / TABWiringCT Measurement VDE TestingInsulation TestProtection Test Market MasterData Registerยง19 EEG Expert assessment recommended for: Grid compatibility ยท Protection concept ยท Commissioning ยท Defect inspection Grid Connection Process swa Netze โ€” Augsburg | Source: PV-BESS-Assessor.com
Since April 2024: Nationwide 800 W inverter power and 2,000 Wp module power. MaStR registration remains mandatory.

Important Documents and Forms

TAB & Requirements (swa Netze) Market Master Data Register VDE-AR-N 4100 Clearingstelle EEG|KWKG

Which transmission system operator is responsible in Augsburg?

Augsburg is located in the TenneT control area. The responsible transmission system operator (TSO) is TenneT TSO GmbH. TenneT is responsible for system stability in the extra-high voltage grid (220/380 kV) and coordinates the feed-in of renewable energy at the transmission grid level. At the regional distribution grid level, Bayernwerk Netz is also an important player.

TSO hierarchy Augsburg: TenneT (transmission grid 220/380 kV) โ†’ swa Netze (distribution grid 0.4-20 kV) โ†’ customer system (PV/BESS). Grid compatibility assessments primarily relate to the distribution grid level (swa Netze); for systems above 1 MWp, coordination with TenneT may be required.
LevelOperatorVoltage LevelRelevance for PV/BESS
Transmission gridTenneT220-380 kVSystem stability, EEG feed-in
Distribution gridswa Netze0.4-20 kVTAB, grid connection, meter location
Customer systemSystem operator0.4 kV (LV)PV array, BESS, inverter

What are typical challenges for PV and BESS in Augsburg?

Augsburg has specific regional characteristics as a location for PV and BESS projects that must be considered during planning and assessment:

UNESCO World Heritage Water Management

Augsburg's historic water management system is a UNESCO World Heritage Site. PV systems in the old town and along the Lech canals require special coordination with the Lower Heritage Protection Authority.

Textile Quarter: Industrial Conversion

The Augsburg Textile Quarter (AKS, Glaspalast) is being converted into residential and commercial districts. The sawtooth roofs of former factories are ideal for PV โ€” however, structural load-bearing capacity must be confirmed by an expert assessment.

LEW and swa Netze: Divided City Territory

In the Augsburg urban area, both swa Netze and Lechwerke (LEW Verteilnetz) are active. The jurisdiction boundary sometimes runs through the middle of residential areas โ€” advance clarification is essential.

Bavarian Solar Mandate in Planning

Bavaria is discussing a solar mandate following the Baden-Wuerttemberg model. As Bavaria's third-largest city, Augsburg would be significantly affected โ€” assessments regarding economic reasonableness are anticipated.

When is an expert assessment advisable?

OccasionOur Service
Acceptance assessmentTAB conformity check, defect report
Dispute with grid operatorIndependent technical evaluation
Systems from 30 kWp / medium voltageSupervision, grid compatibility assessment
Defect assessmentDIN VDE 0100-600, thermography, EL
Capacity bottleneckGrid analysis, alternative concepts

Frequently Asked Questions โ€” TAB swa Netze Augsburg

Which TAB apply to PV systems at swa Netze Augsburg?โ–ผ

VDE-AR-N 4100 and 4105 (low voltage) or 4110 (medium voltage) plus supplementary TAB of swa Netze GmbH.

How do I register a PV system with swa Netze?โ–ผ

Exclusively through a certified electrical contractor. Details: swa Netze website.

Do I need a new meter cabinet in Augsburg?โ–ผ

Must comply with VDE-AR-N 4100 and supplementary TAB. Older cabinets (pre-2010): eHZ, surge protection, SLS. Cost: EUR 1,000-2,500.

How much does a PV or BESS assessment cost in Augsburg?โ–ผ

Depends on system size and scope. Contact: info@pv-bess-assessor.com or +49 89 28 947 920.

When do I need an expert assessment?โ–ผ

For systems from 30 kWp, medium voltage, grid compatibility issues, disputes with the grid operator, acceptance of commercial systems.

Independent PV or BESS assessment in Augsburg?

We know the TAB of swa Netze from daily practice. Get in touch.

Contact Us

Contact Details swa Netze GmbH

Addressswa Netze GmbH, Hoher Weg 1, 86152 Augsburg
Phone0821 6500-8977
Emaileinspeiser.anmeldung@swa-netze.de
Websiteswa Netze โ€” TAB

Related Topics

Last updated: 2026-06-16 | Author: Christoph S. Prestele, TUV-certified expert assessor | Source: swa Netze GmbH